Procurement Lead Time, Inventory Accuracy and Inventory Turnover as Drivers of Schedule and Quality Performance in Construction Companies in Lagos, Nigeria

Authors

  • 1.Mike Ademola Oke 2.Dr. A.Odunsi Author

DOI:

https://doi.org/10.3390/etsq4349

Abstract

 

 

1.Mike Ademola Oke 2.Dr. A.Odunsi

Purpose. Late delivery and defective work remain the two most visible failures of construction projects in Nigeria, and both are routinely traced to the way materials are procured, recorded and moved. This study examines which of five materials inventory management practices (optimising procurement lead time, achieving inventory accuracy, preventing stockouts, optimising inventory turnover and ensuring supplier reliability) explain project completion timelines and project quality in established construction companies in Lagos, Nigeria.

Design/methodology/approach. A cross-sectional survey was conducted among employees of five long-established construction companies headquartered in Lagos State, selected purposively and sampled through stratified proportionate random sampling. Of 371 questionnaires administered, 345 were valid (93.0 per cent). After the measurement model was assessed for reliability and validity, the effects of the five practices on each outcome were estimated by path analysis within a structural equation modelling framework in STATA 17.

Findings. Optimising procurement lead time was the strongest predictor of both completion timelines (β = 0.296, p < 0.001) and project quality (β = 0.267, p = 0.002). Inventory accuracy (β = 0.197, p = 0.007) and inventory turnover (β = 0.144, p = 0.039) also predicted completion timelines, while inventory turnover predicted quality (β = 0.205, p = 0.008). Stockout prevention had no unique effect on either outcome, and supplier reliability fell just short of significance for timelines (p = 0.067).